PPJ #7
- Mia Capoli
- Aug 12, 2019
- 1 min read
Updated: Aug 25, 2019
What I did:
Modeled new Lightning Grail: ~1hr
Textured new lighting Grail: ~2hrs
Edited steampunk and stone floor's contrast: ~.5hrs
Worked with Lange for tiling of floors: ~.5 hrs
Got Playtesters: ~1.5hrs
Adjusted wings on light grail: ~.5hrs
Meetings: ~.5hrs
Total: 6.5 hrs
What went well:
I like how the lightning grail came out!
What went poorly:
The playtesting build for this week was made on monday night which made it extremely hard to get enough playtesters in time.
Next Week:
Polish and extra stuff as needed.
Comments